Introduction
A thermal power station is a power plant
in which the prime mover is steam driven. Water is heated, turns into steam and
spins a steam turbine which either drives an electrical generator or does some
other works, like ship propulsion. After it passes through the turbine, the
steam is condensed in a condenser and recycled to where it was heated. , this
is known as a Rankine cycle. The greatest variation in the design of thermal
power stations is due to the different fuel sources. Some prefer to use the term
energy center because such facilities convert forms of heat energy into
electrical energy.
Commercial electric utility power stations
are m9ost usually constructed on a very large scale and designed for continuous
operation. Electric power plants typically use three phase or individual phase
electrical generators to produce alternating current (AC) electric power at a
frequency of 50Hz or 60Hz depending on its location on the world. Other large
companies or institutions may have their own usually smaller power plants to
supply heating or electricity to their facilities especially if heat or stem is
created anyway for other purposes.
Table of contents
1
|
|
Introduction
|
7
|
2
|
|
TPS
Muzffar Garh
|
8
|
|
2.1
|
Installed
capacity
|
8
|
|
2.2
|
Introduction
to phase#1
|
8
|
|
2.3
|
Introduction
to phase#2
|
9
|
3
|
|
Boiler
|
11
|
|
3.1
|
Water
tube boiler
|
11
|
|
3.2
|
Boiler
parameter
|
11
|
|
3.3
|
Main
part of boiler
|
12
|
|
3.4
|
Boiler
protection
|
16
|
4
|
|
Steam
turbine
|
17
|
|
4.1
|
HP
(High pressure) turbine
|
18
|
|
4.2
|
IP
(Intermediate pressure) turbine
|
18
|
|
4.3
|
LP
(Low pressure) turbine
|
18
|
|
4.4
|
Steam
turbine specification
|
18
|
|
4.5
|
Turbine
protection
|
19
|
5
|
|
FSSS
|
19
|
|
5.1
|
Decanting
area
|
20
|
|
5.2
|
Fuel
oil tanks
|
20
|
|
5.3
|
First
lift pump
|
20
|
|
5.4
|
Main
heaters
|
21
|
|
5.5
|
Second
lift pump
|
21
|
6
|
|
The
generator
|
22
|
|
6.1
|
Working
principle
|
22
|
|
6.2
|
Main
generator parameters
|
23
|
|
6.3
|
Cooling
system of turbo-generator
|
24
|
|
6.4
|
Protections
of generator
|
27
|
7
|
|
Cycles
|
29
|
|
7.1
|
Steam
cycle
|
29
|
|
7.2
|
Fuel
oil cycle
|
30
|
|
7.3
|
Air
flow cycle
|
31
|
|
7.4
|
Condensate
cycle
|
32
|
|
7.5
|
Feed
water cycle
|
33
|
•
T.P.S Muzaffar
Garh
•
Installed
capacity
This power station is a
vital and major thermal power generating installation connected with national
grid system in Pakistan. This power station was constructed in different phases
having total capacity of 1370MW. It consists of:
• Three Russian units of 210MW each
• Two Chinese units of 210MW
• One Chinese unit of 320MW
•
Fuel
Dual fuel combustion
provision gas & furnace oil has been made for all the machines. Furnace oil
is transported through railway wagons and tank Lorries.
Unit#
|
Installed
capacity
|
Working
capacity
|
Constructed
By
|
Construct-ion
Date
|
Fuel
Type
|
ST-1
|
210MW
|
170MW
|
Russian
|
Sep.1993
|
P.
Gas, F. oil
|
ST-2
|
210MW
|
175MW
|
Russian
|
Mar.1994
|
P.
Gas, F. oil
|
ST-3
|
210MW
|
170
MW
|
Russian
|
Feb.1995
|
P.
Gas, F. oil
|
ST-4
|
320MW
|
260MW
|
China
|
Dec.1996
|
P.
Gas, F. oil
|
ST-5
|
210MW
|
170
MW
|
China
|
Dec.1995
|
P.
Gas, F. oil
|
ST-6
|
210MW
|
170
MW
|
China
|
Dec.1995
|
P.
Gas, F. oil
|
Total
|
1370MW
|
1115MW
|
|
Table 1.1 brief views of
TPS units
2.2 Phase#1 (Unit 1, 2 & 3)
This phase consist of three
steam units each capable of generating 210MW electricity. The supplier started
delivery of equipment to site in January, 1989 and after pre-assembly of
equipment at site, erection started in July, 1990. Unit#1 was commissioned in
September, 1993 and unit#2 in March, 1994.
Main Building:
It contains the turbine
hall having a span of 45m and dearator bay, 12m wide. The stem turbines which
drive generators are of three stage condensing type arranged transversely to
the axis of turbine hall. The operational platform is at elevation 12.6m and a
maintenance bay at ground flour near unit#1. The power plant is designed block
principle: boiler-turbine-generator-unit transformer. The flue gas exhaust
section of two units is connected with a 200m high stack, outer section of
which is a 195m high concrete shell.
Combined Auxiliary Building:
The building is connected
with the main building and it houses water treatment plant to produce 100t/h
dematerialized water for the replenishment of station losses. Hydrogen plant to provide
hydrogen for cooling of generator's r rotor, maintenance shops, laboratories,
and central control room.
Fuel & Oil Facilities:
Fuel oil facilities are
constructed for decanting, oil storage, preparation and supply of fuel to boiler
nozzles. It also includes HSD storage as well as oil facilities for reception,
storage, purification and centralized delivery of turbine oil and insulating
oil to power plant.
Hydraulic Structures:
The cooling water used in
condensers is re-circulated in closed cycle with indicated draft cooling
towers, the water is being cooled for each unit in two cooling towers each
consisting of eight fans, two cooling towers carry 27,500Cu m/h circulating
water for condensers of one unit.
Startup Boiler:
One startup boiler using
diesel oil as fuel with steam output of 50t/h is provided to meet steam
requirement for initial start of unit as well as a backup of power plant
auxiliaries. A separate stack of 30m high has been constructed for it.
Electrical Part:
The electricity generated
at 15.75 KV is brought out from unit transformer at 220 KV and feed to the
national grid via a switch yard. Power plant auxiliaries are fed at 6.6 KV.
2.3 Phase#2(Units#5 & 6):
It consist of two units of
210MW each having equipment similar to phase#1. Turbines are placed
longitudinally in main building outdoor boiler exhaust of two units is
connected to one stack.
Overview:
There are many different
types of power plants including thermal power plants and hydel power plants.
Thermal power plants use fuel such as gas, HSD, furnace oil or nuclear fuel to
produce heat energy that is converted to electrical energy through a series of
intermediate process. Hydel power plants convert the potential energy of water
to electrical power as it follows from higher to lower elevations.
The "traditional"
thermal power plant is the Rankin cycle plant named after the man who invented
the cycle. A power plant cycle is a series of processes in which a fluid
generally water/steam, is used to convert heat energy to mechanical energy. The
Rankin cycle in its simplest form consists of a boiler, a turbine, a condenser
and a boiler feed pump. Early plants had thermal efficiencies of approximately
25% to 30%. Only 25% to 30% of the heat energy in the fuel burned in these
plants was converted to electrical energy. The rest was lost in various ways.
The Rankin cycle has been refined considerably over the years and made more
efficient by the addition of components like economizer, feed water heaters,
super heaters and re-heaters. The efficiency of Rankin cycle has also been
improved by increasing the pressure and temperature of the cycle. The laws of
thermodynamics and considerations such as material limitation have prevented
any significant improvement sense then. Power plants commonly use heat rate of
measure efficiency.
Electrical energy
Generator
Mechanical energy
Turbine
Heat Energy
Boiler
Fuel Energy
•
Boiler
The boiler is the main part
of any thermal power plant. It converts the fuel energy into steam energy. The
fuel may be furnace oil, diesel oil, natural gas or coal. The boiler may be
fire from the multiple fuels. The types of boiler use in the T.P.S phase#2 is
"water tube type"
•
Water Tube
Boilers:
In water tube boilers,
boiler water passes through the tubes while the exhaust gasses remain in the
shell side, passing over the tube surface, since tubes can typically withstand
higher internal pressure then the large chamber shell in a fire tube, water
tube boilers are used where high steam pressure (as high as 3,000Psi) are
required.
Water tube boilers are also
capable of high efficiencies and can generate saturated or superheated steam.
The ability of water tube boilers to generate superheated steam makes these
boilers particularly attractive in applications that require dry,
high-pressure, high-energy steam, including steam turbine power generation.
•
Boiler Parameter:
Rated
evaporating amount
|
680t/h
|
Reheat
steam amount
|
575.8t/h
|
Main
steam pressure
|
140Kg/g
|
Temperature
|
541°C
|
Outlet
pressure of reheat system
|
23.8
Kg/g
|
Outlet
temperature of reheat system
|
541°C
|
Inlet
pressure of reheat system
|
25.8
Kg/g
|
Inlet
temperature of reheat system
|
310°C
|
Feed
water temperature
|
251°C
|
Boiler
efficiency (Burn oil)
|
90.26%
|
Boiler
efficiency (Burn gas)
|
85%
|
Exit
gas temperature (Burn oil)
|
153°C
|
Exit
gas temperature (Burn gas)
|
136°C
|
Consumption
of crude oil
|
48.2t/h
|
Consumption
of natural gas
|
59650
N/h
|
•
Main Parts of
Boiler:
The boiler consists of
following main parts:
• Force Draft Fan (FDF)
• Burners
• Furnace
• Up Rise Tube
• Down Comer Tube
• Water Tube
• Super Heater
• Gas Recirculation Fan (GRCF)
• Re-Heater
• Induced Draft Fan (IDF)
• Air
Pre-Heater
• Chimney
• Boiler Drum
• Economizer
•
Force Draft Fan
(FDF)
The force draft fan sucks
the air from atmosphere which is used in the furnace for burning. The air from
the atmosphere is passed through the filter to remove the dust and other
particles from the air. The air from the FDF is then fed to the regenerative
heaters.
The motor of FDF has
following specification:
Type
|
KK
800 11-8
|
Rated
voltage
|
6.6KV
|
Rated
current
|
114/121.3A
|
Rated
speed
|
747rpm
|
Output
|
1000KW
|
Connection
of stator/rotor
|
Y
|
Insulation
class
|
F
|
Permissible
rise
|
80K
|
Ambient
temperature
|
40°C
|
No.
of phases
|
3
|
Rated
frequency
|
50Hz
|
Power
factor
|
0.81
|
Degree
of protection
|
IP54
|
Moment
of inertia
|
310
|
Weight
|
12020/13250
Kg
|
•
Induced Draft Fan
(IDF):
ID fan sucks the flue gases
from the boiler and exhaust through chimney.
The motor of ID fan has
following specifications:
Type
|
KK
800 11-6
|
Rated
voltage
|
6.6KV
|
Rated
current
|
20A
|
Rated
speed
|
991rpm
|
Rated
power
|
2000KW
|
Connection
of stator winding
|
2Y
|
Insulation
class
|
F
|
Permissible
rise
|
80K
|
Ambient
temperature
|
40°C
|
No.
of phases
|
3
|
Rated
frequency
|
50Hz
|
Degree
of protection
|
IP54
|
Moment
of inertia
|
410
|
Weight
|
15970
Kg
|
3.3.3 Gas recirculation
fan (GRCF):
The motor of GRCF has
following specification.
Type
|
KK
400 11-4
|
Rated
voltage
|
6.6KV
|
Rated
current
|
34A
|
Rated
speed
|
1491rpm
|
Rated
power
|
315KW
|
Connection
of stator winding
|
Y
|
Insulation
class
|
F
|
Permissible
rise
|
70K
|
Ambient
temperature
|
50°C
|
No.
of phases
|
3
|
Rated
frequency
|
50Hz
|
Degree
of protection
|
IP54
|
Moment
of inertia
|
11.7
|
Weight
|
•
Kg
|
•
Cooling Towers:
Cooling towers are heat
removal devices used to transform process waste heat to the atmosphere. Cooling
tower may either use the evaporation of water to remove process heat and cool
the working fluid to near the wet-bulb air temperature or relay solely on air
to cool the working fluid to dry –bulb air temperature. Common application includes
cooling the circulating water used in oil refiner, chemical plants and power
station.
•
Circulating water
pump motor:
The motor of the CWP has
following specification:
Type
|
Y1600-12/2150
|
Stator
voltage
|
6.6KV
|
Rated
current
|
182A
|
Rated
speed
|
372rpm
|
Rated
power
|
1600KW
|
Connection
of stator winding
|
2Y
|
Insulation
class
|
B
|
Ambient
temperature
|
50°C
|
No.
of phases
|
3
|
Rated
frequency
|
50Hz
|
Weight
|
17500Kg
|
•
CW Pump:
Type is single stage double
suction centrifugal pump.
Type
|
1400S25-1
|
Capacity
|
16000/h
|
Speed
|
370rpm
|
Power
|
1600KW
|
Weight
|
35000Kg
|
Head
|
25m
|
NP
SHR
|
8.5m
|
•
Air Pre-Heater:
The purpose of the air
pre-heater is to recover heat from the boiler flue gas which increases the
thermal efficiency of the boiler by reducing the useful heat lost in the flue
gas. As a consequence the fuel gases are also sent to the fuel gas stack (or
chimney) at a lower temperature, allowing simplified design of the ducting and
the flue gas stack. It also allows control over the temperature of gases
leaving the stack.
•
Economizer:
Flue gases from large
boilers are typically 450-650°F. Stack economizer recover some of this heat for
pre-heating water. The water is most often used for boiler make-up water are
some other need that coincides with boiler operation. Stack economizers should
be considered as an efficiency measure when large amounts of make-up water are
used (i.e. not all condensate is return to the boiler or large amount of live
steam are used in the process so there is no condensate to return) or there is
a simultaneous need for large quantity of hot water for some other use. The
savings potential is based on existing stack temperature, the volume of make-up
water needed and the hours of operation.
•
Boiler
Protection:
• Fuel protection
• Gas pressure protection
• Diesel oil protection
• Furnace oil protection
• FD fan trip
• ID fan trip
• Regenerative air pre-heating trip
• Drum level high
• Drum level low
• Re-Heat steam pressure drop
• Furnace pressure low
• Furnace flame out
• Natural gas pressure high
•
Steam Turbine
Turbine is used to convert the heat energy
into mechanical energy.
Turbine used in T.P.S Muzaffar Garh is impulse-reaction steam turbine.
The load requirement is controlled by the steam flow through a governing valve.
Maximum steam at full load is 670t/h. When the load at generator is suddenly
decreased then the rpm (frequency) of the generator is increased and to
decrease the frequency we lower down the steam flow which decreases the speed
and maintains the frequency.
If load is suddenly
increased rotor speed becomes slower, to increase the speed, steam flow is
increased.
Steam turbine has three
parts.
• HP turbine
• IP turbine
• LP turbine
(To
re-heater) (From HP Super-heater) (From
re-heater)
Generator
Condenser
HP
(High Pressure) Turbine:
First of all steam from
boiler comes into the HP turbine. Steam in the HP turbine is called live steam
or main steam. Rotor blades diameter of this part of turbine is smallest of the
other parts of the turbine .Inlet steam temperature of the HP turbine is 540 °C
and pressure is 130bar. Outlet steam temperature of the HP turbine is 290°C and
pressure is 15bar. HP turbine has total of 12 stages including one is governing
stage.
•
IP (Intermediate
Pressure) Turbine:
Steam comes into IP turbine from HP
turbine via re-heaters. The steam pressure in this section of turbine is 14bar
and temperature is 540°C. This part has total of 10 pressure stages.
•
LP (Low Pressure)
Turbine:
The outgoing steam of the IP turbine entered
into the LP turbine. Steam from the LP turbine goes into the condenser.
•
Steam Turbine
Specification:
Maximum
load
|
210MW
|
Live
steam pressure
|
132bar
|
Live
steam temperature
|
538°C
|
Rated
speed
|
3000rpm
|
HP
cycle exhaust temperature
|
310°C
|
HP
cycle exhaust pressure
|
24bar
|
Re-Heat
steam temperature
|
538°C
|
Re-Heat
steam pressure
|
14bar
|
•
Turbine
Protection:
• Lube oil pressure (low & high)
• Vacuum drop
• Live steam temperature drop
• Axial shift displacement
• Gas cooling pump tripping
• HP heater level high
• All FWP trip high vibration tripping
• Trip unit by switch/emergency
•
Furnace Safeguard
Supervisory System (FSSS):
• The FSSS station consists of the following
parts:
• Decanting area
• Fuel oil tank
• First lift pump
• Main heater
• Second lift pump
• Diesel pumps
• Recirculation pumps
• Recirculation heater
• Filters
• Control room
•
Decanting Area:
The furnace oil that is
used as a fuel in the burners of the boiler furnace to produce the steam is
transported to the TPS through two ways:
• Oil tankers
• Train
For
unloading of the fuel from oil tankers and train there is separate unloading or de-canting station for
each. The unload fuel oil is initially stored in the underground reservoir;
from there it is filled in the main storage tanks.
02 pumps are used to fill the main storage
tanks from the oil tankers decanting area. One of them is active (on load) and
other is standby.
•
Fuel Oil Tanks:
From the decanting area the furnace oil is
filled in the storage tanks. From there it is supplied to the burners of the
boiler furnace after proper heating.
Usually one storage tank is called service
tank, from there furnace oil is supplied to the units. The furnace oil is
filled in the other tanks first and then filled in the service tank through
recirculation pumps (RCP). The oil in the tanks is kept heated at the
temperature 75-80°C. There are total 06 storage tanks for furnace oil each
having a volume of 20,000 hence each can store 2,00,00,000 litter. There are
two diesel oil storage tanks each having capacity of 1000ton.
•
First Lift Pump:
First lift pump takes the furnace oil from
the service tank and supplied to the main heaters. There are total 04 first
lift pumps which are operated according to unit load conditions. The
specification of first lift pump motor is as follows:
3 phase 50Hz induction motor:
Connection
|
Star
|
Power
|
55KW
|
Power
factor
|
0.9
|
Efficiency
|
90%
|
Voltage
|
230/400V
|
Speed
|
2950rpm
|
Current
|
177/102A
|
•
Main Heaters:
There are 04 main heaters each is
connected to the respective first lift pump. The main heaters heat the furnace
oil through the steam which comes from the boiler. Steam is used to heat the
oil in recirculation heaters. The steam follows through the pipes which heats
the oil outside the tube. The temperature and pressure of the steam in the main
heater is;
• Temperature 270°C
• Pressure 11-13bar
•
Second lift Pump:
Second lift pumps take the furnace oil
from the main heater and supply to boiler of the units. There are 04 second
lift pumps which are operated according to the unit load conditions.
The temperature of oil that is supplied to
the boiler is 105-120°C.
The specification of second lift pump
motor is as:
3 phase 50Hz induction motor:
• Power 250KW
• Voltage 6.6KV
• Speed 2950rpm
• Current 252A
•
The Generator
The generator is a device
which converts the mechanical energy into electrical energy.
•
Working
Principle:
The working principle of generator is based
on the Faraday's
law of electromagnetic induction, which states that:
"The electromotive force is always
produced in conductor which is placed in the magnetic field when there is a
relative motion between conductor and the magnetic field".
If the output electrical energy is AC, it
is called alternator. If the output electrical energy is DC, it is called DC
generator. In fact there is no difference between alternator and Dc generator
except the way the output is obtained from the generator. In alternator the AC
supply is produced in the armature and supply is obtained through slip rings
where as in the DC generator are generated AC supply is obtained from the
armature through the spilt rings or commutator which converts the AC into DC.
The following three things are necessary for generation of electrical energy.
• Magnetic field
• Conductor
• Relative motion between conductor and
magnetic field
In the small generator the magnetic field
is being produced in the stator and the electromotive force is produced in the
rotor through Faraday's law of electromagnetic induction. The electromagnetic
are used in the generator to produce the magnetic field. In the large generator
the magnetic field is produced by the electromagnetic in the rotor and the
electromagnetic force is produced in the stator .the output is taken from the
rotor, the rotor must
Have high insulation due to high voltage
induction and it must have heavy insulation which may increase the size of
rotor, and require more power for the prime mover to rotate to this heavy rotor
•
Main Generator
Parameter:
•
Pilot Exciter:
Type
|
Tfy-46-500
|
Rated
voltage
|
93/161V
|
Rated
current
|
286/165A
|
Rated
speed
|
3000rpm
|
Rated
power factor
|
0.875
|
Phase
|
3
|
Rated
frequency
|
50Hz
|
Armature
connection
|
|
Specification
|
OEA.513.039
|
Manufacturing
date
|
1993-3-1
|
Rated
capacity
|
46KVA
|
•
Alternating Exciter:
Type
|
T1-1165-4
|
Rated
voltage
|
431V
|
Rated
current
|
1562A
|
Rated
speed
|
3000rpm
|
Rated
power factor
|
0.91
|
Phase
|
3
|
Rated
frequency
|
100Hz
|
Armature
connection
|
|
Specification
|
OEA.513.039
|
Manufacturing
date
|
1993-8-24
|
Rated
capacity
|
1165KVA
|
•
Turbine Generator Water Hydrogen Cooled:
Type
|
QFSN-210-2
|
Rated
capacity
|
246MVA
|
Rated
output
|
210MW
|
Rated
voltage
|
15.75KV
|
Rated
current
|
9056A
|
Rated
speed
|
3000rpm
|
Rated
frequency
|
50Hz
|
Phase
|
3
|
Connection
of stator winding
|
2-Y
|
Insulation
class
|
F
|
Power
factor
|
0.85
|
Excitation
voltage
|
289V
|
Excitation
current
|
18.67A
|
Maximum
inlet water temperature for stator winding
|
50°C
|
Maximum
inlet cooling hydrogen
|
50°C
|
Water
flow for stator winding
|
35m2/h
|
Rate
H2 pressure
|
0.3MPa
|
Specification
|
OEA.512.137
|
Manufacturing
date
|
1993-2
|
•
Cooling System of Turbo Generator:
The first question arises here is that why
we need cooling of the generator? As the current flows in the stator and rotor
of the generator is very high so it increases the temperature of the stator and
rotor winding. As the result the resistance of the stator and rotor windings
increases which increase the power losses and may cause the insulation
breakdown.
Two types of cooling are used in the turbo
generator of TPS phase second.
• Stator cooling
• Rotor cooling
•
Stator Cooling:
The stator of the turbo generator is
cooled by distillated or demineralized water. For this purpose a special plant
is installed which prepares the demineralized water for the stator cooling.
This demi water is also used for cooling system of the thirstier converts the
water is passed through the hollow conductor of stator winding for its cooling.
The demi water is necessary for the
cooling of the stator winding because raw water is not a pure insulator which
may cause the flow of leakage current when passed through stator winding.
The demi water plant removes the
impurities and minerals of the raw water and make it good insulator whose
resistivity is taken at a minimum level of 200K.cm. The demi water that process
through the stator winding absorbs the heat of stator winding makes it cool and
becomes hot itself. The demi water then passes through heat exchanger (coolers)
where its temperature is decreased by the circulating water coming from the
cooling towers. This demi water is also passed through the mechanical and
magnetic filters before passing through stator winding and thirstier converts.
•
Water Parameters
in Heat Exchangers:
• Rated temperature of cooled water at
inlet 32°C
• Minimum temperature of cold water 15°C
• Number of gas heat exchangers 02
•
Rated
water flow in on heat exchanger 150m3/h
•
Rotor Cooling:
The rotor cooling is done by H2
gas. Hydrogen is used for the following purposes:
• Its heat exchange capability is much
better than other gases.
• It is very lighter than other gases so do
not overload the rotor.
• Its preparation is very easy and cheap.
Hydrogen gas is filled in the generator
and maintained at a pressure of 4Kg/cm2. It takes all the heat of
the rotor and cools the rotor winding and gets warmed it. For the cooling of
the gas there are four gas cooler inside the generator on each corner.
Circulating water of the cooling tower is used in the gas cooler for hydrogen
cooling.
Hydrogen gas is explosive if it is
combined with oxygen under pressure so too avoid any leakage of gas and
entrance of air inside the generator the rotor assembly is sealed by the seal
oil whose pressure is at least 0.7Kg/cm2 more than hydrogen gas
inside the generator.
When the generator is turned off for a
long time for maintenance purpose hydrogen is released from the generator in
the air using special method. Method involves that firstly fill the generator
with CO2 which release the hydrogen in the air and then in the end
air is filled in the generator and CO2 is released in the air. This
method is adopted because if hydrogen is released using air instead of CO2
then it can cause explosion due to oxygen in the air which will meet hydrogen
under pressure in the generator. After maintenance hydrogen gas is refilled in
the generator using the reverse process as described above.
•
Water Parameters
in Gas Cooler:
• Rated temperature of cold water at
inlet 32°C
• Minimum temperature of cold water 15°C
• Maximum water pressure 3Kg/cm2
• Number of gas cooler
04
• Rated water flow in on gas cooler 76.5m3/h
•
Protections of
Generator:
The following protections are installed
for the protection of the generator in TPS.
•
Longitudinal
Differential Current Protection:
This system is intended to protect against
multiphase short circuit in generator stator winding and its leads including
against double earth fault, one of which being the generator.
•
Lateral
Differential Current Protection:
This system is intended to protect against
turn-to-turn short circuit of one phase in the generator stator winding.
•
Earth Fault
Protection of Stator Winding:
This system is intended to reveal and
disconnect one phase earth fault of generator stator winding.
•
Differential
Protection of the Unit:
This system is intended to backup
longitudinal differential protection of generator.
•
Negative Sequence
Current Protection:
This system is intended to prevent damage
of generator increase of overloading by negative sequence current caused by
asymmetric load or external asymmetric short circuit and abnormal operating
condition of power grid.
•
Over Current
Protection Against Overloading of Generator:
This system is intended for signaling at
symmetric overloading of generator stator.
•
External
Symmetrical Short Circuit Protection:
This system is intended to protect the
generator against external symmetric short circuit.
•
Protection Against
Asynchronous mode, when excitation loss:
This system is intended to protect against
asynchronous mode. One of the elements of resistance block relay for protection
of the unit against external symmetrical short circuit used.
•
Protection of
Generator Rotor Against Overloading:
This system is intended to protect against
overloading under emergency condition as well as increase of failure of
generator excitation system which cause long term flow of current of abnormal
value along the rotor winding.
•
Earth Fault
Protection In One Point of excitation Circuit:
This system is intended to protect the
generator incase of earth fault at one point of excitation circuit.
•
Protection
Against Voltage Increase At Generator At Ideal Operation:
This system is intended to prevent in admissible increase in voltage at
turbo-generator and transformer of unit during ideal operation of the unit
incase of failure of excitation system.
•
Zero Sequence
Current Protection:
This system is intended to backup
protection at one phase short circuit in 220KV network. It is also used to
backup unit protection when short circuit at the 220KV side of the unit.
•
Differential
Protection of the Exciter:
This system is intended to protect against
all kind of short circuit in the exciter winding and on its leads.
•
Over Current
Protection of Exciter Against External Short Circuit:
This system is intended to protect against
over current in the external system of the exciter.
•
CYCLES
•
Steam Cycle:
•
Fuel Oil Cycle:
Flue Gases
Air Pre-Heater
ID Fan
Exhaust (Chimney)
Fuel Oil Cycle
Burners (Boiler)
Gate & Quick Closing Valves
Oil Heaters
Furnace Oil Tanks
•
Air Flow Cycle:
Economizer
Environment
FD Fan
Calorifire
Stock
ID Fan
A.P.H
Furnace
G.R.C Fans
Flue Gases Fresh Air
•
Condensate Water
Cycle:
Condenser
Hot
well
Dearator
LP
Heater B
LP
Heater A
Cond. Storage Tank
Cond. Pump
Makeup
Water
DA
Pump
From LP Heater
Detractor
•
Feed Water Cycle:
To
Economizer
HP Heater B
HP Heater A
P-8 P-14 BFP C
BFP B
BFP A
Make up water
YOU ARE RIGHT -- INDIA WILL NEVER CALL CO2 A BAD GAS --IT IS LIFE SUSTAINING ..MAN MADE CO2 DOES NOT AFFECT THE CLIMATE..
ReplyDeletebuy weed seeds